Winter Street Bridge

The construction cost of the Winter Street Bridge over the Sudbury River is $5,551,576,85. Construction is to start in the Fall of 2012 and be completed by 2015.

The proposed project involves the replacement of two single span bridges carrying Winter Street over the Sudbury River in Framingham. The proposed bridge will be a two-span concrete structure and constructed wider to provide vehicular, bicycle and ADA accommodation. The horizontal and vertical alignments will remain essentially the same. Staged construction will be used to maintain vehicular and pedestrian traffic during construction.

About a mile down the street the Winter Street bride over the railroad track will be completed by spring 2014 at an estimated $7.1 million. Construction is schedule to start in the summer of 2011.

 